...
Blog

Setting realistic expectations

Psicologia
Settembre 04, 2025
Setting realistic expectationsSetting realistic expectations">

Define three concrete targets for the next 30 days and review progress weekly. Keep metrics simple, attach owners, and fix deadlines for each milestone to prevent scope creep.

Choose targets that are achievable and directly tied to current resources. For example, if your team can reliably complete two tasks per week, set a cap of six tasks in 21 days per person, with a contingency of 15% for interruption. Track completion rate, cycle time, and quality on a single pannello di controllo that updates every Friday.

Base the targets on data from the recent past. Pull performance from the prior 12 weeks: average weekly output, typical delay, and common interruption days. If the prior data show 2.4 tasks per week with 0.6 delays per week, round to reachable numbers and admit a 10–20% cushion for variability.

During the weekly check, compare results with the plan. If you miss a milestone by more than two days twice in a row, either adjust scope by removing a lower-priority item or extend the deadline by a single week. Ensure all changes are communicated to stakeholders in 24 hours.

Aim for transparent communication: share the targets, the data, and the rationale. When teams understand the why and the how, decisions become quicker and less stressful. Use a short recap at the end of each week to align on remaining work and next steps.

Consolidate learning into the next cycle: preserve what works, drop what doesn’t, and formalize a plan for the following period with new measurable targets. Keep the cadence steady, prevent overcommitment, and protect time for quality checks.

Define SMART milestones with concrete deadlines

Define SMART milestones with concrete deadlines

Assign a specific due date to each milestone and attach a measurable outcome.

Specific: outline the exact deliverable, assign ownership, and define clear acceptance criteria. Example: “Prototype onboarding flow ready for review by 2025-09-18; owner: Sam; criteria: passes UX review with no critical issues.”

Measurable: attach numbers or binary checks so progress is trackable. Examples: conduct 15 user interviews, complete 3 key features, or achieve a release readiness score of 90% with all critical tests passed.

Achievable: assess available resources, skills, and dependencies; break large goals into 1–2 week steps; assign one developer and one designer where possible; include a 2-day cushion for unexpected delays.

Relevant: verify each milestone directly advances the core objective; remove tasks that do not contribute within the planned window to prevent scope creep.

Time-bound: set hard deadlines, establish biweekly reviews, and require sign-off before moving to the next stage. Use fixed sprint windows to maintain momentum.

Example plan: By 2025-09-18, complete 15 user interviews and document findings; By 2025-09-25, finalize feature scope and UI mockups; By 2025-10-09, implement core interactions; By 2025-10-23, run usability tests with 8 participants; By 2025-11-01, launch private beta to 100 users; By 2025-11-15, address the top 5 issues and prepare for public release.

Estimate time, budget, and resources and map dependencies

Start with a task ledger, assign owners, and apply three-point estimates for duration. Use optimistic, most likely, and pessimistic values to compute a weighted duration and reserve a time margin for risk.

Estimate task sizes in hours: small 4–8 h, medium 8–24 h, large 24–72 h. For multi-day tasks, break into sub-tasks of 4–6 h chunks to improve precision. For each task, record optimistic, most likely, and pessimistic values: O, M, P, then compute expected = (O + 4M + P)/6.

Aggregate to determine total duration and calendar slot. Example: 12 tasks at average 14 h = 168 h. Team of two people working 40 h per week yields 80 h per week. Weeks = 168/80 = 2.1. Add 20% margin: ~2.5 weeks. Plan a safe window of 3 weeks with scheduled reviews after week 1 and week 2.

Budget estimate = total hours × blended rate. Example: rates: developer $50/h, tester $40/h, designer $60/h. Using an average of $55/h, cost = 168 h × $55/h = $9,240. Add 15% buffer → $10,626.

Resource planning: ensure tasks are assigned to people with the needed skills; cap weekly load at 40 h per person; distribute work to minimize bottlenecks; keep a small reserve of expertise for spike work; consider a freelancer option for peak periods.

Dependencies: build a map that links tasks to predecessors; mark those on the critical path; compute earliest start and finish; set milestones at Weeks 1–3; apply soft constraints and review gates after each milestone; update the map as risks evolve.

Monitoraggio: definire la baseline del piano e monitorare i dati effettivi settimanalmente; se la varianza di qualsiasi attività supera 15%, adeguare le stime e riallineare la linea di base; comunicare tempestivamente agli stakeholder il programma e il budget rivisti.

Crea un ciclo di feedback per la ricalibrazione e gli aggiornamenti continui

Crea un ciclo di feedback per la ricalibrazione e gli aggiornamenti continui

Raccomandazione: Avvia uno sprint di calibrazione bisettimanale con una dashboard live che monitora le metriche target, i risultati degli utenti e lo stato di salute del sistema, e assegna un unico responsabile per gli aggiornamenti.

Input di dati provengono da analisi del prodotto, feedback degli utenti e log operativi. Definisci un insieme compatto di indicatori anticipatori (tasso di adozione delle funzionalità, time-to-value, tasso di errore) e indicatori ritardatari (retention, punteggio di soddisfazione). Richiedi dati più recenti di 24 ore dopo ogni ciclo.

Durante la revisione dello sprint, confronta i risultati effettivi con gli obiettivi, attribuisci le deviazioni a cause concrete e decidi gli adeguamenti alle soglie o alle strategie. Registra le decisioni in un documento dinamico e crea una versione di ogni aggiornamento per preservare la cronologia.

Ruoli e responsabilità: designare un proprietario dei dati, un product owner e un proprietario tecnico. Ognuno è responsabile della qualità dei dati, della logica delle decisioni e della comunicazione tempestiva alle parti interessate.

Meccanismo di aggiornamento: ricalibrare le soglie e gli obiettivi dopo ogni ciclo. Se i risultati migliorano, aumentare gradualmente le soglie; in caso contrario, modificare le tattiche o l'ambito. Includere il tempo previsto per vedere l'impatto e una chiara regola di decadenza se i risultati si bloccano.

Esempio pratico: Obiettivo: aumentare il completamento dell'onboarding al 65% entro 6 settimane. Attuale: 42%. Azione: semplificare i passaggi dell'onboarding, aggiungere suggerimenti in-app, eseguire un micro-sondaggio dopo la prima sessione. Aumento previsto: 15–20% entro due cicli. Monitorare con la dashboard e rivedere nello sprint successivo.

Guardrail di qualità: verificare l'integrità dei dati, evitare il cherry-picking, mantenere un ambito ristretto per ogni ricalibrazione ed evitare l'overfitting alle fluttuazioni a breve termine.

Checklist di implementazione: definire le metriche, stabilire le fonti di dati, assegnare i responsabili, impostare la cadenza, creare modelli di revisione e definire un programma per gli aggiornamenti.

Per saperne di più sull'argomento Psicologia
Iscriversi al corso